U.S. Supremes Deny Emergency Request by Va. Landowners to Stop MVP

A small group of uppity Virginia landowners don’t want Mountain Valley Pipeline (MVP) crossing their horse pastures, leaving a mark. So they conspired with Big Green lawyers in a lawsuit challenging the right of the Federal Energy Regulatory Commission (FERC) to use eminent domain to build pipelines across private land. In October, the landowners filed…

Read More...

Equitrans Midstream, Builder of MVP, Considers Selling Itself

Although we should have expected this, the news that Equitrans Midstream, builder of the 303-mile Mountain Valley Pipeline (MVP) project, is looking at possibly selling itself comes as a gut punch. We suppose it hits us that way because we feel as though we’ve been in the trenches with Equitrans from the beginning, fighting to…

Read More...

MVP Gets FERC Permission to Drill 24/7 Under Interstate 81 in Va.

More progress to report on finishing the 94% completed (now likely closer to 97% completed) Mountain Valley Pipeline (MVP) project. MVP needs to cross under Interstate 81 in Montgomery County, VA, and it’s no small challenge to drill under the highway because it’s solid rock. On Oct. 13, MVP (being built by Equitrans Midstream) filed…

Read More...

MVP Sues Two Protesters for Conspiracy, Blocking Pipe Construction

In September, Mountain Valley Pipeline (MVP), which has been hassled and harassed endlessly by so-called “protesters” and foreign-backed Big Green groups, sued some 40 protesters and two Big Green groups for $4 million for their ongoing illegal activity to block the final bits of the 303-mile project (see MVP Files Lawsuit Against Anti Groups, Protesters…

Read More...

Equitrans Says MVP Will Become One of Most Valuable Pipes in U.S.

Equitrans Midstream issued its third quarter update yesterday. As you might expect, there was much talk about completing the nearly-done Mountain Valley Pipeline (MVP) project. Near the top of Equitrans’ 3Q official update is this comment from CEO Thomas Karam: “Once in-service, there is little doubt MVP will be one of the most valuable pipelines…

Read More...

PA AG Files Criminal Charges Against Equitrans for Home Explosion

In 2018, a man in Clarksville (Green County), PA, turned on his gas stove, and it exploded, catching fire and leveling the entire house (see Did Shale Well Methane Migration Cause SWPA Home to Explode?). The man, his girlfriend, and young child were helicoptered to a hospital burn unit. The early working theory/assumptions were (a)…

Read More...

DC Circuit Denies Anti Request to Block MVP Construction in Va.

Shrill antis have their answer from the U.S. Court of Appeals for the District of Columbia (D.C. Circuit) in a request to (once again) shut down construction on the Mountain Valley Pipeline (MVP): NO! A small group of uppity Virginia landowners don’t want MVP crossing their horse pastures, leaving a mark. So they conspired with…

Read More...

How MVP’s Latest Delay to 1Q24 Affects Project’s Partners, Customers

Last week, MDN brought you the news that the 303-mile Mountain Valley Pipeline (MVP) will not be completely done and online until sometime in the first quarter of 2024 (see Equitrans Admits the Obvious – MVP Won’t be Online Until 2024). In addition to this further delay, Equitrans, the company building MVP, said the cost…

Read More...

Shrill Antis Get More Shrill Asking Court to Block MVP Construction

A long-running lawsuit filed by Big Green groups using (abusing) a small group of uppity Virginia landowners argues the Federal Energy Regulatory Commission (FERC) had no right to delegate authority to Mountain Valley Pipeline (MVP) to use eminent domain to cross land, including the land owned by the small group of uppity landowners in Virginia….

Read More...

Equitrans Admits the Obvious – MVP Won’t be Online Until 2024

Just two days ago, MDN brought you a post about the challenges faced by Equitrans Midstream in completing the 303-mile Mountain Valley Pipeline project this year (see MVP Hits Construction Challenges – Will it Get Done in 2023?). Our exact words in that post: “The brutal truth is that it will be really hard to…

Read More...

Desperate Antis Ask DC Circuit to Block MVP Construction 1 More Time

A long-running lawsuit filed by Big Green groups using (abusing) a small group of uppity Virginia landowners argues the Federal Energy Regulatory Commission (FERC) had no right to delegate authority to Mountain Valley Pipeline (MVP) to use eminent domain to cross land, including the land owned by the small group of uppity landowners in Virginia….

Read More...

3 Out-of-State Protesters Arrested for Blocking MVP Construction

This is growing tiresome. Appalachians Against Pipelines, a group backed with big money from Big Green, continues to funnel paid “protesters” to construction sites for the 95% completed Mountain Valley Pipeline (MVP), mainly in Montgomery County, Va., who chain themselves to equipment requiring state troopers to carefully remove them (requiring hours), slowing the already challenging…

Read More...

Va. County Judge Refuses to Stop Illegal Activities of MVP Protesters

Emily Satterwhite, who teaches Appalachian studies at Virginia Tech and has been engaged in illegal activities against the Mountain Valley Pipeline (MVP) going back more than five years (see our previous stories about Satterwhite here). Satterwhite continues to encourage others to join illegal MVP construction blockades. On Friday, MVP asked a Montgomery County judge to…

Read More...

NC Legislature Overrides Gov. Veto of Bill to Help MVP Southgate

Equitrans Midstream, the builder of the 303-mile Mountain Valley Pipeline (MVP) project, wants to extend the pipeline by an extra 75 miles from the current terminus in Pittsylvania County, VA, to Alamance County, NC, to provide natural gas for heating and electric generation. The extension is called MVP Southgate. In typical fashion, Democrats oppose it,…

Read More...

MVP Protesters Block Construction in Jefferson National Forest

Radicalized protesters who have been brainwashed (and paid) by Big Green liars continue their campaign to prevent the construction of the final 5% or so of the Mountain Valley Pipeline (MVP). This past Saturday, a protester calling himself Mickey, from the group Appalachians Against Pipelines, locked his arms in a “sleeping dragon” device, blocking construction…